You use the Risks lists in Microsoft Office Project Web Access to identify and log risks. For each risk, you want to specify a resource who will own the risk and mitigate it until it is closed. In Project Web Access, you need a reminder to appear on the Home page of the resource when you assign the risk. What should you do?
A.
Enter the resource name in the Owner field.
B.
Enter the resource name in the Assigned To field.
C.
Enter the resource name in the Mitigation field.
D.
Link the risk to a task that the resource is working on.