You need to set up the tracking method for this project without disrupting other projects

Your company uses Microsoft Office Project Server 2007. The default tracking method is percent complete. For a single project, you have permission to track tasks based on total actual work. You need to set up the tracking method for this project without disrupting other projects. What should you do?

Your company uses Microsoft Office Project Server 2007. The default tracking method is percent complete. For a single project, you have permission to track tasks based on total actual work. You need to set up the tracking method for this project without disrupting other projects. What should you do?

A.
In Microsoft Project Web Access, change the Project Server default settings to percent complete.

B.
In Microsoft Project Web Access, change the Project Server settings to actual hours and remaining work.

C.
In Microsoft Office Project Professional 2007, change the collaboration options for the project to actual hours and remaining work.

D.
In Microsoft Office Project Professional 2007, change the collaboration options for the project to percent complete.