What type of view should you create?

In a group of projects that are saved to Microsoft Office Project Server 2007, a custom field categorizes the projects by type. You are asked to create a view that displays a bar chart based on the type of project each resource has worked on for the past 2 years. You need to create a view in Microsoft Office Project Web Access so that you can generate this bar chart. What type of view should you create?

In a group of projects that are saved to Microsoft Office Project Server 2007, a custom field categorizes the projects by type. You are asked to create a view that displays a bar chart based on the type of project each resource has worked on for the past 2 years. You need to create a view in Microsoft Office Project Web Access so that you can generate this bar chart. What type of view should you create?

A.
Resource Center

B.
Resource Assignments

C.
Data Analysis

D.
Team Tasks