You need to ensure that all project managers use a custom view that includes these fields when they develop their project plans

Your organization uses Microsoft Office Project Server 2007. A number of task enterprise custom fields have been defined. You need to ensure that all project managers use a custom view that includes these fields when they develop their project plans. What should you do?

Your organization uses Microsoft Office Project Server 2007. A number of task enterprise custom fields have been defined. You need to ensure that all project managers use a custom view that includes these fields when they develop their project plans. What should you do?

A.
In a blank project, add the task custom fields to a custom view, and then save the project as an enterprise template.

B.
Use the Organizer to add the task custom fields to their projects.

C.
Add the task custom fields to your project workspace site template.

D.
Add the task custom fields to a custom view in the Enterprise Global template.