An activity plan that is published to Microsoft Office Project Server 2007 has a task scheduled to take 5 more days. The resource assigned to the task tells you that the task requires 2 more days, instead of 5 more days. In Microsoft Office Project Web Access, you need to update the task so that dependent tasks will be rescheduled. What should you do?
A.
Delete the task in the activity plan, create a new task with 2 days duration, and assign the resource to the new task.
B.
Edit the task details to reduce the duration by 3 days.
C.
Accept the resource timesheet with actual time worked by the resource, but reject the task update.
D.
Submit a surrogate timesheet for the resource with the difference in work reported as administrative non-working time.