You need to ensure that holiday time for each enterprise resource is accounted for in the project plan

You manage a project that is published to Microsoft Office Project Server 2007. The project resources are located in several countries. Each country has a different set of national holidays. You need to ensure that holiday time for each enterprise resource is accounted for in the project plan. What should you do?

You manage a project that is published to Microsoft Office Project Server 2007. The project resources are located in several countries. Each country has a different set of national holidays. You need to ensure that holiday time for each enterprise resource is accounted for in the project plan. What should you do?

A.
In Microsoft Office Project Professional 2007, create a local calendar for each country, and then assign resources to their respective country calendars.

B.
In Microsoft Office Project Web Access, create an enterprise calendar for each country, and then assign resources to their respective country calendars.

C.
In Microsoft Office Project Web Access, create an enterprise calendar for the country in which corporate headquarters is located, and then assign resources to that calendar.

D.
In Microsoft Office Project Web Access, create an enterprise calendar for the country in which most of the project work will be completed, and then assign resources to that calendar.