In a project that is published to Microsoft Office Project Server 2007, a task is scheduled to take 20 hours of work over 4 days. Although only 1 day has elapsed and 5 hours of work have been performed on the task, you receive timesheet and task update information indicating that the task is 50 percent complete. In Microsoft Office Project Web Access, you need to update your published project plan with this information. What should you do?
A.
On the Task Updates page, accept the task update.
B.
On the Timesheet Approvals page, approve the timesheet that includes the task.
C.
On the Timesheet Approvals page, reject the timesheet that includes the task.
D.
On the Review Timesheet Detail page, ensure that the actual work on the task is 10 hours so that the percentage complete will be computed as 50%, and then approve the timesheet that includes the task.