You manage a portfolio of projects that are saved to Microsoft Office Project Server 2007. Your organization is evaluating whether to take on another project. A key factor in that decision is whether the necessary resources will be available during the next 3 months. Your organization’s resources include full-time and part-time regular employees and some contractors with variable schedules. You need to check resource availability to ascertain how much free time the resources required for the new project will have during the next 3 months. What should you do?
A.
In Microsoft Office Project Web Access, on the Resource Center page, display the assignments for the selected resources.
B.
In Microsoft Office Project Web Access, on the Resource Center page, display the availability for the selected resources.
C.
In Microsoft Office Project Web Access, on the Data Analysis page, create a pivot table showing the work, baseline work, and actual work of the required resources for the next 3 months.
D.
In Microsoft Office Project Professional 2007, in the Task Usage view, display the assignments for the next 3 months.