You are tracking a project that is published to Microsoft Office Project Server 2007. Your organization tracks actual hours on the project level, not on the task level. Some of your resources do not have access to a computer and submit their hours on paper timesheets each week.
You need to record their time. What should you do?
A.
In Microsoft Office Project Web Access, enter their hours in a resource plan.
B.
In Microsoft Office Project Web Access, enter their hours in surrogate timesheets.
C.
In Microsoft Office Project Web Access, enter their hours as planned administrative time.
D.
In Microsoft Office Project Professional 2007, update their actual hours in the Resource Usage view.