You create a project with a generic project team. The project is saved to Microsoft Office Project Server 2007. In Microsoft Office Project Professional 2007, you need to assign resources with specific skills to tasks, and then replace them with named resources. The named resources need to see their new assignments. What should you do?
A.
Assign generic resources to the tasks, and then publish the project plan.
B.
Assign generic resources to the tasks. Use the team builder to add named resources to your project plan, and then save it.
C.
Assign yourself to all tasks. Use the Resource Substitution Wizard to replace the assignments, and then publish the project plan.
D.
Assign generic resources to the tasks. Use the Resource Substitution Wizard to replace assignments, and then publish the project plan.