you need to assign named resources to tasks in the proposal so that their availability is updated

A proposal is saved to Microsoft Office Project Server 2007. In Microsoft Office Project Web Access, you need to assign named resources to tasks in the proposal so that their availability is updated. What should you do?

A proposal is saved to Microsoft Office Project Server 2007. In Microsoft Office Project Web Access, you need to assign named resources to tasks in the proposal so that their availability is updated. What should you do?

A.
Create a resource plan that uses named resources, and then save it.

B.
Use the team builder to assign generic resources to the proposal, and then publish it.

C.
Use the team builder to assign named resources to the proposal, and then publish it.

D.
Use the team builder to assign named resources to the proposal, and then save it.