you need to commit a named resource from the enterprise resource pool

A project plan that is saved to Microsoft Office Project Server 2007 currently proposes generic resources for all tasks. For each generic resource, you need to commit a named resource from the enterprise resource pool. This resource must be available to work on your project.
What should you do?

A project plan that is saved to Microsoft Office Project Server 2007 currently proposes generic resources for all tasks. For each generic resource, you need to commit a named resource from the enterprise resource pool. This resource must be available to work on your project.
What should you do?

A.
Use a filter that will exclude generic resources and include only enterprise resources with availability during your project. Replace each generic resource with an enterprise resource, and then book that resource as Committed.

B.
Use a filter that will locate generic resources with availability during your project. Replace each generic resource with an enterprise resource, and then book that resource as Committed.

C.
Use a filter that will exclude generic resources and include only enterprise resources with availability during your project. Replace each generic resource with an enterprise resource, and then use Assign Resources to modify each assignment for this resource and demand the resource assignment.

D.
Use a filter that will exclude generic resources. Replace each generic resource with an enterprise resource, and then use Assign Resources to modify each assignment for this resource and demand the resource assignment.
Finally, level all resources to ensure that they have availability.