In Microsoft Office Project Professional 2007, your program manager has created a program schedule with a Deliverables list representing key milestones. You need to display the differences between dates for program milestones and project milestones when they change. What should you do?
A.
Copy the program milestones to the Deliverables list of the project workspace site.
B.
Manage dependencies on deliverables, and create a link to a task.
C.
Manage dependencies on deliverables, but do not create a link to a task.
D.
Insert your project and the program schedule into a master project, and then create start-to-finish dependencies between tasks for project and program milestones.