you need to escalate the risk to an issue, without losing the historical record of the risk

A project that is published to Microsoft Office Project Server 2007 has a risk associated with a task involving delivery of critical parts. You are notified that the parts vendor will be unable to deliver the parts on time, which will delay the entire project by 2 weeks. In Microsoft Office Project Web Access, you need to escalate the risk to an issue, without losing the historical record of the risk. What should you do?

A project that is published to Microsoft Office Project Server 2007 has a risk associated with a task involving delivery of critical parts. You are notified that the parts vendor will be unable to deliver the parts on time, which will delay the entire project by 2 weeks. In Microsoft Office Project Web Access, you need to escalate the risk to an issue, without losing the historical record of the risk. What should you do?

A.
Assign the risk to your manager.

B.
Create an issue. Link it to the risk, and then close the risk.

C.
Create an issue. Copy the risk information into the issue, and then delete the risk.

D.
Add the task to the hot issues section of your status report, and then submit your status report.