In a set of projects that are saved to Microsoft Office Project Server 2007, a custom field is used to indicate project status. You are asked to create a report listing all Active and Completed projects. The report should display graphical indicators to show whether the projects are within budget and schedule. You need to create a view in Microsoft Office Project Web Access so that you can generate this report. What type of view should you create?
A.
Project Center
B.
Data Analysis
C.
Team Tasks
D.
Resource Assignments