You are working on a project that is saved to Microsoft Office Project Server 2007. Your mentor, who is not your project manager or resource manager, asks you to provide a record of lessons learned based on your observations of overall operations. You need to provide this record on a weekly basis. What should you do?

You are working on a project that is saved to Microsoft Office Project Server 2007. Your mentor, who is not your project manager or resource manager, asks you to provide a record of lessons learned based on your observations of overall operations. You need to provide this record on a weekly basis. What should you do?

A.
Every week, create a task, and add a comment.

B.
Every week, add a line to your timesheet, and add a comment.

C.
Submit an unrequested status report.

D.
Create a status report request.