A project plan in Microsoft Office Project Server 2007 has a dependency on a deliverable from a preceding project plan. The deliverable has been delayed. You need to display the new dates of the deliverable in the Gantt Chart view and revise the dates of your current project plan.
What should you do?
A.
Add a new dependency, and then rebaseline the project plan.
B.
Add a new dependency, and then reschedule the project plan to start after the completion of the deliverable.
C.
Accept all server changes, and then rebaseline the project plan.
D.
Accept all server changes, and then reschedule the project plan to start after the completion of the deliverable.