You need to incorporate the task updates of local resources into your plan so that you can analyze the progress made by each resource

You are tracking a project that is published to Microsoft Office Project Server 2007. In the project plan, some of your resources are local. You need to incorporate the task updates of local resources into your plan so that you can analyze the progress made by each resource.
What should you do?

You are tracking a project that is published to Microsoft Office Project Server 2007. In the project plan, some of your resources are local. You need to incorporate the task updates of local resources into your plan so that you can analyze the progress made by each resource.
What should you do?

A.
In Microsoft Office Project Web Access, assign the tasks performed by the local resources to yourself. Post their hours into your own task updates.

B.
In Microsoft Office Project Web Access, assign the tasks performed by the local resources to a generic resource.

C.
In Microsoft Office Project Web Access, add the tasks to your own timesheet as activities, and then track the hours spent by the local resources within those activities.

D.
In Microsoft Office Project Professional 2007, record the hours for the local resources.