You assign support tasks to part-time resources in Microsoft Office Project Web Access. Part-time resources have a calendar of fewer than 40 hours per week. You need to make the assignments without having access to Microsoft Office Project Professional 2007. Where should you make the assignments?
A.
To the resource plan of a project plan
B.
To the resource plan of a proposal
C.
To the resource plan of an activity
D.
To the tasks of an activity