You publish a task assignment to a resource with 16 hours of work in Microsoft Office Project Server 2007. The resource updates the task with 8 hours of actual work. A note in the task tells you that the task is already completed despite the original estimate. You need to update the task so that it is listed as completed, without modifying the actual work. What should you do?
A.
Change the % Complete field to 100%.
B.
Change the % Work Complete field to 100%.
C.
Change the Actual Duration field to 2 days.
D.
Change the Remaining Work field to 0 hours.