You need to confirm that these resources have no other enterprise project work scheduled for next week

You manage a project that is saved to Microsoft Office Project Server 2007. You want to know whether the programmers on your team have time to work on your project next week. You dont want to interfere with any tasks scheduled for other projects. You need to confirm that these resources have no other enterprise project work scheduled for next week. What should you do?

You manage a project that is saved to Microsoft Office Project Server 2007. You want to know whether the programmers on your team have time to work on your project next week. You dont want to interfere with any tasks scheduled for other projects. You need to confirm that these resources have no other enterprise project work scheduled for next week. What should you do?

A.
In Microsoft Office Project Professional 2007, display your project plan in the Resource Sheet view.

B.
In Microsoft Office Project Web Access, select the resources, and display the View Availability view.

C.
In Microsoft Office Project Web Access, display your project plan in the Resources Summary view.

D.
In Microsoft Office Project Web Access, view the unsubmitted timesheets for the resources.