You need to find a temporary solution so that the resource’s timesheet can be submitted on time

A resource assigned to a project that is published to Microsoft Office Project Server 2007 cannot access Project Server. Timesheets are due this afternoon, and the resource needs to indicate that she worked 6 hours instead of the planned 8. You need to find a temporary solution so that the resource’s timesheet can be submitted on time. What should you do?

A resource assigned to a project that is published to Microsoft Office Project Server 2007 cannot access Project Server. Timesheets are due this afternoon, and the resource needs to indicate that she worked 6 hours instead of the planned 8. You need to find a temporary solution so that the resource’s timesheet can be submitted on time. What should you do?

A.
In Microsoft Office Project Web Access, create and submit a surrogate timesheet for the resource for this time period.

B.
In Microsoft Office Project Web Access, have the system administrator log on as the resource and use the Replace Actual With Planned feature for the task worked on.

C.
In Microsoft Office Project Professional 2007, update the task performed by the resource to indicate actual work done for the week.

D.
In Microsoft Office Project Professional 2007, assign the task performed by the resource to another resource.