You need to change the project status to Active

In a project that is saved to Microsoft Office Project Server 2007, the value of a custom field for project status is Proposed. You need to change the project status to Active. What should you do?

In a project that is saved to Microsoft Office Project Server 2007, the value of a custom field for project status is Proposed. You need to change the project status to Active. What should you do?

A.
In Microsoft Office Project Web Access, on the Project Center page, edit the properties of the project plan by setting the custom field for project status to Active.

B.
In Microsoft Office Project Web Access, on the Project Center page, use the Build Team function to change the booking type of the project resources from Proposed to Committed.

C.
On the project workspace site, create a status column in the Deliverables list, and then set the default value of the column to Active.

D.
On the project workspace site, create a status column in the Project Documents library, and then set the default value of the column to Active.