You manage the resources assigned to a project that is published to Microsoft Office Project Server 2007. When you review the resource timesheets in Project Server, you see that a resource has recorded 80 hours for 1 day of work. You decide the entry should be 8 hours. You need to ensure that the timesheet is corrected. What should you do?
A.
In Microsoft Office Project Web Access, on the Timesheet Approvals page, reduce the hours from 80 to 8.
B.
Adjust the time by converting 72 hours to administrative time for that day.
C.
Create a surrogate timesheet for the resource, and then enter the correct number of hours there.
D.
Import the timesheet into task updates, and then adjust the task updates.