You need to resolve the problem the PMO manager encountered when creating a Data Analysis view. What should you do?
A.
Republish all project plans.
B.
Check the queue and process all outstanding jobs.
C.
Add the new view to the PMO manager’s security profile.
D.
Add the new custom field to the cube as a new cube dimension, using the cube configuration.