You need to be able to identify tasks that place the project schedule at risk according to the PMO standards. What should you do?
A.
Add a Finish Date column to the Project Center Tracking view.
B.
Add a Finish Date column to the Project Details Tasks Schedule view.
C.
Add a Finish Variance column to the Project Details Tasks Schedule view.
D.
Add a column to the Project Center Tracking view for all projects that displays Finish Variance.