You need to ensure that the managements requirement for contingency tracking on delays is in place.
What should you do?
A.
Create a resource plan for the project.
B.
Create a new activity plan from the Project Center for project contingencies.
C.
Create a risk in the project workspace, and assign it to the person responsible for creating the contingency plan.
D.
Create an issue in the project workspace, and assign it to the person responsible for creating the contingency plan.