You’ve recently approved a project that is scheduled to begin in two months. You need to evaluate resource availability for the next six months. What should you do?
A.
Set the value in a custom project status field to Approved.
B.
Publish all assignments for the project plan to Project Server.
C.
Replace all generic resources with proposed enterprise resources.
D.
Replace all generic resources with committed enterprise resources.