You need to create the basis for logging of non-project activities identified by the CEO. In Project Web Access, what should you do?
A.
Create administrative time categories for vacations, meetings, administration, and miscellaneous.
B.
In each project, create tasks for non-project time categories such as vacations, meetings, administration, and miscellaneous.
C.
Set up your own project with logging processes for vacations, meetings, administration, and miscellaneous; and assign resources to the appropriate task, when they are not assigned elsewhere.
D.
Set up a project named Administrative Time with tasks for vacations, meetings, administration, and miscellaneous. Instruct team members to self-assign themselves to these tasks when they are not working on project tasks.