You need to create the resources in your company’s resource pool so that the new staffing model will be implemented during the initial stages of a project

You need to create the resources in your company’s resource pool so that the new staffing model will be implemented during the initial stages of a project. What should you do?

You need to create the resources in your company’s resource pool so that the new staffing model will be implemented during the initial stages of a project. What should you do?

A.
Create a cost-type resource named generic.

B.
Create a work-type resource named generic.

C.
Create a work-type resource for each qualification.

D.
Create a generic work-type resource for each qualification.