You need to meet Holly Holts reporting requirement. What should you do?
A.
Modify the Task Cost view by adding a field named Budget cost.
B.
Modify the Project Center Cost view by adding a field named Budget cost.
C.
Modify the Project Center Cost view by adding a field named Budget work.
D.
Create a new Project Center view named Cost and add the following fields: Project name, Start date, Completion date, Budget, Costs, and Cost forecast.