In order to comply with the new government rules, you need to create a system that requires resources to account for all hours worked, by project. How should you have resources enter their time?
A.
Team members complete weekly timesheets.
B.
Team members update task status by entering progress daily.
C.
Project managers enter the completion percentage for each task into the project plan.
D.
Project managers enter the actual work performed each day for each task into the project plan.