You need to meet management’s requirement for estimated cost to completion reporting. What should you do?
A.
Create a Data Analysis view displaying only the Cost Variance field.
B.
Create a Project Center view displaying only the Remaining Cost field.
C.
Create a report displaying only the Cost Variance field, by using the Report Wizard.
D.
Create a report displaying only the Remaining Cost field, by using the Visual Report feature.