You need to forecast resource requirements for a task. What should you do?
A.
Assign generic local resources to the tasks.
B.
Assign generic enterprise resources to the tasks.
C.
Assign named enterprise resources to the tasks based on multiple skills.
D.
Assign named enterprise resources to the tasks based on Resource Breakdown Structure (RBS).