You need to find out why Amy Strande does not see values in the two fields in the Project Center view. What should you do?
A.
Republish the project with the current data.
B.
Set the Status date to the project start date.
C.
Set the baseline and the status date for the project.
D.
Set the Earned Value tracking method to Physical % Complete.