You need to respond to managements schedule request for the Package Infrastructure project. You have identified affected tasks and available resources. What should you do next?
A.
Assign resources to effort driven tasks.
B.
Assign resources to fixed duration tasks at 80% units.
C.
Assign resources to fixed duration tasks at 10% units.
D.
Assign resources to fixed duration tasks at 20% units.