You need to create the program cost report as requested by the CEO. What should you do?
A.
Create a visual report in Microsoft Office Project Professional 2007 with budget and cost fields.
B.
Create an enterprise project custom field for programs. Then create a Project Center view of projects grouped by program, with budget and cost fields.
C.
Create an enterprise project custom field for programs. Then create a Data Analysis view of projects grouped by program, with budget and cost fields.
D.
Create an enterprise resource custom field for programs. Then create a Resource Center view of resources grouped by program, with budget and cost fields.