You need to help Maria view her testing resource assignments

You need to help Maria view her testing resource assignments. What should you do?

You need to help Maria view her testing resource assignments. What should you do?

A.
Create a Project Detail view that displays resource assignments.

B.
In Microsoft Office Project Professional 2007, create a Resource Usage view.

C.
Create a Data Analysis view that displays work and availability by resource and by month.

D.
Create a Data Analysis view that displays work and baseline work by project and by month.