You need to manage nonproject time to fulfill the accounting department’s requirements

You need to manage nonproject time to fulfill the accounting department’s requirements. What should you do?

You need to manage nonproject time to fulfill the accounting department’s requirements. What should you do?

A.
Set up Administrative Time categories for only nonworking time.

B.
Set up one enterprise project for each category of administrative time.

C.
Set up an enterprise project with one task for each category of administrative time.

D.
Set up Administrative Time categories for both nonproject time and nonworking time.