In Project Web Access, what should you do?

You need to address management’s requirements for identifying phase completion delays. In Project Web Access, what should you do?

You need to address management’s requirements for identifying phase completion delays. In Project Web Access, what should you do?

A.
Create a Project Detail view that contains the column for work variance.

B.
Create a Project Detail view that contains the column for finish variance.

C.
In the project workspace, add the Risks list Web Part to the main page.

D.
In the project workspace, create a risk called Phase Completion, and create a contingency plan for the risk.