What should you do?

You must create resource assignments for a newly proposed project. What should you do?

You must create resource assignments for a newly proposed project. What should you do?

A.
Assign resources to the plan as Proposed.

B.
Assign resources to the plan as Committed.

C.
Assign team resources to the project plan.

D.
Assign generic resources to the project plan.