You need to implement the Testing teams task-assignment requirement

You need to implement the Testing teams task-assignment requirement. What should you do?

You need to implement the Testing teams task-assignment requirement. What should you do?

A.
Create a generic resource. Assign all tasks to the generic resource.

B.
In Microsoft Office Project Professional 2007, set the booking type of each resource to Proposed.

C.
Create a Team Resource. Assign all tasks to the Team Resource. Assign all the Testing team members to the same Team Resource.

D.
Assign generic resources to the project. Instruct the Testing team leader to assign specific resources to tasks by using the matching function in Project Web Access.