You are the program manager. You need to analyze and track the changes in the program. What should you do?
A.
Open one of the independent projects, and link to the other projects using deliverables. Save and publish the project to the project server. Use the Task Sheet view to analyze and track the changes.
B.
Insert the three independent projects into a new program. Save and publish the master project to the project server. Use the Tracking Gantt view to analyze and track the changes.
C.
Copy all tasks of the three independent projects into a new project. Save and publish the project to the project server. Use the Tracking Gantt view to analyze and track the changes.
D.
Copy all tasks of the three independent projects into a new project. Save and publish the project to the project server. Use the Task Sheet view to analyze and track the changes.