You need to update the Northwind2U program to reflect the change of resource, and then deliver the requested report

You need to update the Northwind2U program to reflect the change of resource, and then deliver the requested report. What should you do before you begin the update?

You need to update the Northwind2U program to reflect the change of resource, and then deliver the requested report. What should you do before you begin the update?

A.
Overwrite the default baseline for reporting purposes.

B.
Set a baseline that has not previously been used for reporting purposes.

C.
Create a copy of the project on the server for comparison to the updated project.

D.
Save a copy of the project as a Microsoft Office Project Professional 2007 project file.



Leave a Reply 0