You need to ensure that this client computer is successfully deployed with the modified task sequence

You are using Windows Deployment Services (WDS) and System Center Configuration Manager 2007 R2 to perform a Zero Touch Installation (ZTI) of Windows 7 on your company’s client computers. A user shuts down his computer during the deployment process. Before the computer boots, the task sequence is modified.

You need to ensure that this client computer is successfully deployed with the modified task sequence.

What should you do first?

You are using Windows Deployment Services (WDS) and System Center Configuration Manager 2007 R2 to perform a Zero Touch Installation (ZTI) of Windows 7 on your company’s client computers. A user shuts down his computer during the deployment process. Before the computer boots, the task sequence is modified.

You need to ensure that this client computer is successfully deployed with the modified task sequence.

What should you do first?

A.
Delete the C:\MININT and C:\_SMSTaskSequence folders.

B.
Delete the BootStrap.ini and CustomSettings.ini configuration files.

C.
Run the WDSUTIL /disconnect-Client command.

D.
Run the WDSUTIL /replace-Image command.