You create a Resource Breakdown Structure (RBS) in your Microsoft Office Project Server 2007 environment. Some resources are not yet assigned to project tasks. You need to create a Data Analysis view that displays assigned and unassigned resources within each branch of the RBS. What should you do?
A.
Add the RBS_Resource dimension to the Resource cube. Build the OLAP cube.
B.
Add the RBS_R_Assignment dimension to the Assignment cube. Build the OLAP cube.
C.
Restart SQL Server Analysis Services on the Microsoft SQL Server computer.
D.
Create a new Data Analysis view based on the Resource Timephased cube.