You need to ensure that users are able to view the most recent project data

In your Microsoft Office Project Server 2007 environment, users report that the Data Analysis views do not include the most recent project data. You configure the PWA cube build settings to use the earliest project start date and the latest project finish date. You successfully rebuild the cube. The recent project data is still not included. You need to ensure that users are able to view the most recent project data. What should you do?

In your Microsoft Office Project Server 2007 environment, users report that the Data Analysis views do not include the most recent project data. You configure the PWA cube build settings to use the earliest project start date and the latest project finish date. You successfully rebuild the cube. The recent project data is still not included. You need to ensure that users are able to view the most recent project data. What should you do?

A.
Delete the current default Data Analysis view and create a new one. Manually rebuild the OLAP cube.

B.
Open and save each project that has the data that must be included. Manually rebuild the OLAP cube.

C.
Publish the projects that have the data that must be included. Manually rebuild the OLAP cube.

D.
Remove enterprise custom fields from the OLAP cube configuration. Manually rebuild the OLAP cube.