What are two possible ways to achieve this goal?

You are a manager for a project your team has been working on for many weeks. Your project is
created as a Microsoft SharePoint task list project and is available in Project Center.
You have established the work breakdown structure (WBS), predecessors, assignments, and all of
the functionalities you can get from a SharePoint task list. However, the project has grown in detail,
and managing 200 activities has become difficult in Project Web App (PWA).
You need to ensure resources continue to report their progress in the same way.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.
Choose two.)

You are a manager for a project your team has been working on for many weeks. Your project is
created as a Microsoft SharePoint task list project and is available in Project Center.
You have established the work breakdown structure (WBS), predecessors, assignments, and all of
the functionalities you can get from a SharePoint task list. However, the project has grown in detail,
and managing 200 activities has become difficult in Project Web App (PWA).
You need to ensure resources continue to report their progress in the same way.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.
Choose two.)

A.
Activate the Enterprise Project Features for the SharePoint site task list and edit the tasks in PWA
project details.

B.
Edit the project in Project Professional 2013 from the Project Center by clicking the icon of the
SharePoint task list project in the Indicators column.

C.
Activate the Enterprise Project Features for the SharePoint site task list and edit the tasks in
Project Professional 2013.

D.
Edit the project in Project Professional 2013 by synching the SharePoint task list so you can take
advantage of the extended features.