You are a project manager for an organization that uses Project Server 2013.
You create a complex schedule that has many segments which are divided by your organization’s
departments and external vendors. The duration of the schedule is 18 months. After six months, you
learn that a different department may do some of the upcoming work.
While upper management decides which department they need to perform the work, you realize
that your schedule has numerous assignments that now may be done by another department. You
do not want to delete the assignments because you have many inter-dependencies among these
tasks and the rest of your schedule. However, you cannot have resources working on these tasks at
this time.
You need to keep your tasks in your schedule so upper management can view them, and you need to
ensure that the team members do not work on or update those tasks.
What should you do?
A.
Lock the tasks
B.
Inactivate the tasks
C.
Set the tasks to manually scheduled
D.
Delete the tasks