Which page should you use?

You are a team member in an organization that uses Project Server 2013. Each week you report
progress on multiple projects that are managed as Microsoft SharePoint task lists.
You need to update task progress on multiple projects from one page.
Which page should you use?

You are a team member in an organization that uses Project Server 2013. Each week you report
progress on multiple projects that are managed as Microsoft SharePoint task lists.
You need to update task progress on multiple projects from one page.
Which page should you use?

A.
Tasks page in Project Web App (PWA)

B.
My Tasks page in Newsfeed

C.
Tasks page in a Project site

D.
Timesheet page in Project Web App (PWA)